8-7-09
I've spent the last week or two helping Molly McGath with the graffiti removal project. I have also been preparing for the Preservation in you Community poster presentations that will take place on Tuesday August 11th. I will be presenting th…
7-13-09
We have spent weeks trying to figure out what is wrong with the chamber. We are slowly going through all the possibilities for not getting an SO2 reading on the analyzer. SO2 has to flow out of the SO2 tank and through a valve in order to en…
6-17-09
The SO2 Calibration will be completed on Thursday. The chamber will be completly calibrated on Friday (fingers crossed). The first samples may be starting on Monday.
This past week, the SO2 motor froze up and was replaced. This is what will…
Salutations, my name is Eric Guidry. I will be a senior at the Scholars' College at Northwester State University. I am from Sulphur LA. The next few days, I will be working with the the SO2 chamber, trying to get it running. In the first week I have…